TUGAS NETWORK PLANNING PAK YO
| Kegiatan | Yang men | Waktu Normal | Waktu | Biaya | |||
| dahului | a | M | b | Crash | Normal | Crash | |
| A | - | 3 | 4 | 5 | 3 | 100000 | 160000 |
| B | - | 5 | 6 | 8 | 5 | 100000 | 160000 |
| C | A | 2 | 3 | 5 | 3 | 75000 | 75000 |
| D | B | 2 | 3 | 5 | 3 | 90000 | 90000 |
| E | B | 3 | 4 | 5 | 3 | 120000 | 160000 |
| F | C | 3 | 4 | 5 | 3 | 160000 | 200000 |
| G | C | 3 | 4 | 5 | 3 | 100000 | 130000 |
| H | D | 2 | 3 | 5 | 3 | 100000 | 100000 |
| I | E | 4 | 5 | 6 | 4 | 200000 | 260000 |
| J | F | 4 | 5 | 6 | 4 | 200000 | 260000 |
| K | G | 4 | 5 | 6 | 5 | 150000 | 150000 |
| L | JK | 2 | 4 | 6 | 3 | 100000 | 140000 |
| M | HI | 2 | 3 | 5 | 2 | 40000 | 130000 |
| N | LM | 2 | 3 | 5 | 3 | 75000 | 110000 |
| Dari tabel diatas, coba sudara buat : | ||||
| a. | Network dalam keadaan normal dan total biaya ? | |||
| b. | Crash program (cukup satu kali) dn total biaya ? | |||
| c. | Tentukan probabilitas pekerjaan tersebut agar dapat | |||
| diselesaikan pada waktunya ? | ||||